Halle, Belgium

During working activities at a crossroads in Halle, Ghent Dredging asked Van Heck to provide a pump for the temporary diversion of the sewage system.

In the centre of the city

To ensure a minimum of noise and disturbance, Van Heck delivered a super silenced diesel driven HK500 pump. The working activities are being carried out in the city centre. The pump delivers a flow rate of about 3,000 m³/h.

The pipework has been buried (see photo) so that the cranes are not hindered in doing their jobs.

The temporary detour will last until late April.